In March 2021, the Veterans Benefits Administration (VBA) began transitioning to a Digital GI Bill platform designed to improve education benefits delivery. The original plan called for implementing the new platform through a contractor for 10 years at a projected cost of $453 million. The VA Office of Inspector General (OIG) conducted this audit to assess VBA’s progress in implementing the platform.The OIG found VBA encountered delays due to unclear contract requirements and unrealistic expectations. The original contract required VA to provide three test environments by October 2022, but resource and infrastructure limitations resulted in only one test environment, which was undergoing testing in January 2024. Further, the platform relies on the decommissioning of older systems such as the Benefits Delivery Network (BDN); however, BDN’s decommissioning has been pushed back from September 2023 to as late as spring 2025, which will delay platform completion and may increase costs.The OIG found VBA did not follow the Government Accountability Office’s best practices for a project’s integrated master schedule, which plots a project’s entire scope. Until February 2023, the platform project had no overall master schedule, and once one was established, it was not consistently shared with the contractor. The OIG also found that poor communication contributed to failures in the critical path—a schedule’s continuous sequence of activities—that resulted in delays and increased costs.VBA has renegotiated the original contract, further delaying implementation and increasing project costs by $479 million, more than doubling the original contract to $932 million.The OIG made three recommendations to the under secretary for benefits to increase the chances of successful implementation under the new contract through better monitoring, stronger communication with the platform contractor, a consistent and updated master schedule, strategies to address critical path failures, and a clear timeline.
Report Date | Agency Reviewed / Investigated | Report Title | Type | Location | |
---|---|---|---|---|---|
Department of Veterans Affairs | VBA Needs to Improve Oversight of the Digital GI Bill Platform | Audit | Agency-Wide | View Report | |
Nuclear Regulatory Commission | System Review Report on the Nuclear Regulatory Commission’s Office of the Inspector General Audit Organization | Peer Review of OIG | Agency-Wide | View Report | |
U.S. Postal Service | Effectiveness of the New Regional Processing and Distribution Center in Atlanta, GA | Audit |
|
View Report | |
Department of Health & Human Services | South Carolina Did Not Always Invoice Rebates to Manufacturers for Physician-Administered Drugs Dispensed to Enrollees of Medicaid Managed-Care Organizations | Audit | Agency-Wide | View Report | |
Department of Transportation | Summary Report on Significant Single Audit Findings Impacting DOT Programs for the 3-Month Period Ending June 30, 2024 | Audit | Agency-Wide | View Report | |
U.S. Agency for International Development | USAID's Gaza Response: External Factors Impaired Distribution of Humanitarian Assistance Through the JLOTS Maritime Corridor | Inspection / Evaluation |
|
View Report | |
U.S. Agency for International Development | Financial Audit of Bangladesh YouthRise Managed by BBC Media Action, Grant 72038821GR00002, April 1, 2022, to March 31, 2023 | Other |
|
View Report | |
U.S. Agency for International Development | Financial Audit of Generating Rural Opportunities by the Working with Cooperatives Project in the Philippines, Managed by AgriterraPhils Inc., Agreement 72049220CA00002, January 6, 2020, to December 31, 2021 | Other |
|
View Report | |
U.S. Agency for International Development | Financial Audit of Norwegian Refugee Council Under Multiple USAID Agreements, for the Year Ended December 31, 2021 | Other |
|
View Report | |
Export-Import Bank | Evaluation of EXIM’s Environmentally Beneficial Goods and Services Mandate | Inspection / Evaluation | Agency-Wide | View Report | |