An official website of the United States government
Here's how you know
Official websites use .gov
A .gov website belongs to an official government organization in the United States.
Secure .gov websites use HTTPS
A lock (
) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.
Brought to you by the Council of the Inspectors General on Integrity and Efficiency
Federal Reports
Report Date
Agency Reviewed / Investigated
Report Title
Type
Location
Gulf Coast Ecosystem Restoration Council
FINANCIAL MANAGEMENT: Audit of the Gulf Coast Ecosystem Restoration Council’s Financial Statements for Fiscal Years 2024 and 2023
At the request of the Tennessee Valley Authority’s (TVA) Supply Chain, we examined the cost proposal submitted by a contractor for engineering services in connection with the validation phase of TVA’s Small Modular Reactor and Clinch River Nuclear project. Our examination objective was to determine if the cost proposal was fairly stated for a planned $25 million contract.
In our opinion, the cost proposal was overstated. Specifically, the proposed labor markup and other direct cost rates were overstated compared to recent actual costs. Additionally, (1) the proposed maximum wage ranges were not reflective of contractor’s actual wage ranges and (2) to the draft contract should be revised to clarify language regarding fee and long-term travel. We suggest TVA management (1) negotiate reduced labor markup and other direct cost rates to more accurately reflect the contractor’s recent actual costs, (2) negotiate revisions to the proposed wage ranges to more accurately reflect contractor’s actual wage ranges, and (3) revise the draft contract to clarify TVA’s intent regarding fee and long-term travel.
EAC OIG, through the independent public accounting firm of Allmond & Company, LLC, audited EAC’s financial statements for the fiscal year ended September 30, 2024.
EAC OIG, through the independent public accounting firm of Allmond & Company, LLC, audited EAC's financial statements for fiscal year 2024. The purpose of this letter is to convey information concerning control weaknesses that did not rise to the level of a significant deficiency or material weakness.