An official website of the United States government
Here's how you know
Official websites use .gov
A .gov website belongs to an official government organization in the United States.
Secure .gov websites use HTTPS
A lock (
) or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.
Brought to you by the Council of the Inspectors General on Integrity and Efficiency
Federal Reports
Report Date
Agency Reviewed / Investigated
Report Title
Type
Location
Department of Health & Human Services
Medicare Compliance Review of Houston Methodist Hospital for 2012 and 2013
Houston Methodist Hospital (the Hospital) located in Houston, Texas, complied with Medicare billing requirements for 111 of the 159 inpatient and outpatient claims we reviewed. However, the Hospital did not fully comply with Medicare billing requirements for the remaining 48 claims, resulting in net overpayments of $609,000 for the audit period. Additionally, the Hospital did not fully comply with Medicare billing requirements for three of the five separate inpatient claims we reviewed, resulting in overpayments of $68,000. On the basis of our sample results, we estimated that the Hospital received approximately $1.3 million in overpayments from Medicare.
The OIG audited costs billed to the Tennessee Valley Authority (TVA) by ABB, Inc. (ABB), for providing large and medium power transformers under Contract No. 4645. Our audit included $83.3 million in costs paid by TVA between June 1, 2011, and March 31, 2015. Our objective was to determine if the costs billed to TVA were in compliance with the contract terms and conditions. In summary, we determined TVA missed payment discount opportunities of $1,029,965, including (1) $936,596 due to incorrect payment terms input into the Maximo system on purchase orders (PO) for which TVA opted to make progress payments, and (2) $93,369 for POs for which TVA opted not to make progress payments. Also, ABB overbilled TVA $155,577 for transformer and other costs, and TVA is due a $188,000 rebate for a transformer that had been purchased. In addition, we noted several opportunities to improve contract administration by TVA. Specifically, we found (1) ABB billed TVA $10,293,437 for materials, equipment, and services not provided for under the contract scope of work; (2) TVA payments exceeded the contract monetary limits; (3) ABB billed TVA $506,592 for instrument transformer purchases that should have been ordered and paid for under a different contract TVA had with ABB; and (4) ABB had not provided the price adjustment formulas for each transformer design type required by the contract. TVA management (1) changed the contract payment terms in the Maximo system on March 21, 2014, from Net 45 days to 2 percent-16 days/Net 45 days, which corrected the problem of missed payment discount opportunities when TVA had opted to make progress payments, and (2) issued Contract Amendment No. 4, effective July 28, 2015, which partially addressed the contract scope of work and fully addressed the price adjustment formulas. However, the contract scope of work needs to be further amended to include materials and services.(Summary Only)
Cornerstone Hospital of Southwest Louisiana (the Hospital) in Sulphur, Louisiana, did not comply with Medicare requirements for billing Kwashiorkor on any of the 52 claims that we reviewed. The Hospital used diagnosis code 260 for Kwashiorkor but should have used codes for other forms of malnutrition. The 52 inpatient claims that were coded incorrectly resulted in overpayments of $343,000. Hospital officials believe that all claims identified by OIG were appropriately submitted for payment.