On Monday December 22, 2008, the ash containment area at the Kingston Fossil Plant failed. Approximately 5.4 million cubic yards of fly ash and bottom ash were released onto land and adjacent waterways. As part of the OIG's ongoing commitment to provide oversight of the Kingston ash spill cleanup, we reviewed TVA's non-time-critical Kingston Ash Recovery Project activities.The objectives of this review were to determine (1) the overall status of the non-time-critical phase of the Kingston Ash Recovery Project and (2) if TVA is meeting the schedule for non-time-critical activities. During our review, we found that TVA has made significant progress in the non-time-critical phase of the Kingston Ash Recovery Project. Specifically, TVA has recently completed the following activities: (1) removing ash from the North Embayment, (2) buttressing of Dike C, (3) transferring a portion of a nearby ball field to the Kingston Fossil Plant, and (4) replacing the skimmer wall in the intake channel. In addition, TVA has ongoing non-time-critical activities that include: excavating ash from the Middle Embayment, constructing the Perimeter Wall Stabilization around the on-site disposal areas, disposing of ash on-site, studying the effects of residual ash on the river system, and creating a master plan for park and recreation areas. While TVA is making progress in the completion of non-time-critical activities, we found that five of nine activities reviewed did not meet the scheduled completion date. If the project continues late completion of activities, there is an increased risk that the overall project completion date of 2015, disclosed in the company's financial statements, could be delayed.We recommend TVA's Senior Vice President, Generation Construction, evaluate the current schedule to determine if the identified delays have caused overall schedule slippage. If it is determined that the overall schedule will be delayed beyond the date disclosed in the footnotes to TVA's financial statements, then the disclosure should be updated. TVA management agreed with our recommendation and has taken actions to address it.
Report Date | Agency Reviewed / Investigated | Report Title | Type | Location | |
---|---|---|---|---|---|
Tennessee Valley Authority | Review of Non-Time Critical Kingston Ash Recovery Project Activities | Audit | Agency-Wide | View Report | |
Appalachian Regional Commission | Hale County Hospital Electronic Medical Records System | Audit |
|
View Report | |
U.S. Agency for International Development | Review of USAID Cooperative Development Programs | Audit |
|
View Report | |
U.S. Agency for International Development | Audit of USAID's Office of Foreign Disaster Assistance Activities in Zimbabwe | Audit |
|
View Report | |
National Archives and Records Administration | Audit of NARA's Data Center Consolidation Initiative | Audit | Agency-Wide | View Report | |
Department of the Treasury | SAFETY AND SOUNDNESS: Failed Bank Review of SCB Bank | Audit | Agency-Wide | View Report | |
Appalachian Regional Commission | Appalachian State University - Higher Education | Audit |
|
View Report | |
Tennessee Valley Authority | Audit of Westinghouse Material Escalation billings under Contract 65717 | Audit | Agency-Wide | View Report | |
U.S. Agency for International Development | Audit of USAID/Ghana's Efforts to Integrate Gender Into HIV/AIDS Activities | Audit |
|
View Report | |
U.S. Agency for International Development | Management Letter: Follow-up Audit of the Millennium Challenge Corporation's Implementation of Key Components of a Privacy Program for its Information Technology Systems | Other | Agency-Wide | View Report | |