The Joint Polar Satellite System: Cost Growth and Schedule Delay of a Key Instrument Acquisition Highlight the Need for Closer Attention to Contractor Oversight
Our objective was to assess the cost, schedule, and technical performance of the Program’s acquisition and development effort for selected instruments. We found the following: (1) The Program exceeded contract definitization timelines and conducted late and abbreviated baseline reviews. (2) JPSS-2...