335

Distributor Review of Electric Power Board (Chattanooga)

2010
2009-12593
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG performed a review of the City of Chattanooga Electric Power Board (Chattanooga) which is based in Chattanooga, Tennessee and a distributor of TVA power. Our review of Chattanooga found issues involving customer classification and metering that could impact (1) the proper reporting of...

Review of a contractor's tool program for WBN Unit 2 construction project

2010
2009-12968
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

We reviewed a contractor's tool program for the Watts Bar Nuclear plant (WBN) Unit 2 construction project. Our objective was to assess the procedures and key control activities used to track and account for tools used in the Watts Bar Nuclear (WBN) Unit 2 construction project. Our review of the WBN...

Peer Review of the Stability Analysis of Dike C at the Kingston Fossil Plant

2010
2009-12910-01
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

TVA Office of the Inspector General retained Marshall Miller & Associates, Inc. (Marshall Miller) to conduct a peer review of the report entitled "Report of Geotechnical Exploration and Slope Stability for Dike C," prepared by Stantec Consulting Services, Inc. (Stantec) of Lexington, Kentucky. In...

Contract for Geotechnical Services

2010
2009-12878
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

We performed an audit $3.3 million in payments made by TVA to a contractor for geotechnical services between January 2003 and July 15, 2009. In summary, we determined the contractor overbilled TVA $395,479 as follows:$216,865 in labor costs, including (1) $110,016 due to the use of hourly billing...

Review of TVA's Environmental Performance Results

2010
2007-11402
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

This review was the fourth in a series of reviews that will benchmark TVA's performance in key areas and answer the question, "How is TVA doing in regard to environmental performance." In conducting this review we: (1) assessed environmental performance, including key performance measures and, (2)...

Contract for Quality Control Inspections and Nondestructive Examinations

2010
2009-12349
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

As part of our annual audit plan, we audited $35.07 million in costs billed to TVA by a contractor for providing quality control inspections and nondestructive examinations under two contracts. In summary, we found TVA had been overbilled $159,662 under one of the contracts, including (1) $136,030...

Distributor Review of Scottsboro Electric Power Board

2010
2009-12510
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG performed a review of the City of Scottsboro Electric Power Board (Scottsboro) which is a distributor for TVA power based in Scottsboro, Alabama. Scottsboro also operates a telecommunications department that offers cable, internet, and telephone services. Also, Scottsboro is one of four...

Review of Contractor's Management of Subcontractors

2010
2009-12916
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

We reviewed the design of a TVA contractor's process for administering subcontracted work for the Watts Bar Nuclear Plant Unit 2 construction project. Specifically, we reviewed the contractor's (1) invoice review process, (2) process for scheduling work, and (3) process for ensuring subcontractor...

Distributor Review of Lenoir City Utilities Board

2010
2009-12594
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

OIG reviewed the Lenoir City Utilities Board (LCUB), a distributor for TVA power based in Lenoir City, Tennessee. LCUB also operates nonelectric businesses that include gas, water, and sewer utilities. The OIG's review found multiple concerns, including (1) customer classification and metering...