Distributor Audit of Warren Rural Electric Cooperative Corporation

2011
2010-13286
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited Warren Rural Electric Cooperative Corporation's (WRECC) compliance with its power contract with TVA. WRECC is a power distributor based in Bowling Green, Kentucky. For fiscal year 2010, WRECC provided power to approximately 60,000 customers that resulted in revenues of approximately...

Distributor Audit of Sevier County Electric System

2011
2010-13661
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited Sevier County Electric System's compliance with the power contract between the TVA and Sevier, a power distributor based in Sevierville, Tennessee, for the period July 2008 through June 2010. For fiscal year 2010, Sevier provided power to approximately 54,000 customers that resulted...

Review of the Effectiveness of TVA's Transmission Line Maintenance Program

2011
2010-13280
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

As part of our annual audit plan, we reviewed the inspection and maintenance programs for TVA's transmission lines and structures. Specifically, we identified (1) instances in which transmission lines were not assigned a preventive maintenance inspection interval, (2) improvements that could be made...

Distributor Audit of City of Oak Ridge

2011
2009-12595
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

As part of our annual audit plan, the OIG (Office of the Inspector General) audited the Oak Ridge, Tennessee, electric system for compliance with the power contract with the Tennessee Valley Authority (TVA) for the period July 2007 through June 2009. Key contract provisions included (1) proper...

Section 26a Process Review

2011
2010-13407
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG evaluated key aspects of TVA's Section 26a process for effectiveness and efficiency. We determined (1) costs may not be fairly and consistently applied and opportunities exist to improve the cost-recovery process, (2) processes could be improved in the examination and use of customer...

Williams Specialty Services - Subcontractor Services to Bechtel Power Corporation

2011
2010-13678
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

We audited $9.58 million of costs billed to Bechtel Power Corporation (Bechtel) and subsequently to TVA by Williams Specialty Services, LLC (WSS) for asbestos abatement and valve refurbishment services at Watts Bar Nuclear Plant Unit 2 (WBN U2) under a subcontract agreement. We found the costs...

Distributor Audit of BVU Authority

2011
2010-13660
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited the electric system of BVU Authority (BVU), a distributor of TVA power based in Bristol, Virginia. The objective of the audit was to determine compliance with key provisions of the power contract between TVA and BVU for the period July 2008 through June 2010. For fiscal year 2010...

TVA's Plan for Removal of Polychlorinated Biphenyl (PCB) Equipment

2011
2009-12943
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The objective of this review was to determine whether TVA was meeting all requirements and planned actions for the removal of equipment containing polychlorinated biphenyls (PCBs). We found there were currently no requirements for the removal of PCB equipment, and previous planned actions for PCB...

Review of TVA's Fossil Fire Protection Systems

2011
2010-13530
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The objective of this review was to determine if the fire protection systems were adequately maintained and mitigating actions are taken to minimize the impacts of fires at TVA fossil plants. During our review, we identified a number of issues related to fire protection at TVA fossil plants. We...

History, Status, and Alternatives: TVA Financial Flexibility

2011
2009-13007-01
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

TVA's challenges are great with the need for financial flexibility to ensure the TVA mission of delivering low cost power is achieved. The current debt ceiling could limit TVA's financial flexibility and require TVA to seek higher cost financing options or require significant rate increases that...