Distributor Audit of Meriwether Lewis Electric Cooperative

2012
2010-13659
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited the electric system of Meriwether Lewis Electric Cooperative (MLEC), a distributor based in Centerville, Tennessee. The objective of the audit was to determine compliance with provisions of the power contract between TVA and MLEC for the audit period July 2008 through June 2010. For...

Review of TVA's Compliance with IPIA FY 2011

2012
2011-14340-01
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The Office of the Inspector General performed an audit of the TVA's compliance with the Improper Payment Information Act (IPIA) for FY 2011. In summary, we found TVA was in compliance with IPIA requirements that were applicable to TVA. In our opinion, TVA was only required to comply with the IPIA...

Audit of Westinghouse Material Escalation billings under Contract 65717

2012
2011-14150
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we audited Westinghouse Electric Company LLC's billed and estimated remaining material escalation costs under Contract No. 65717. In summary, we determined Westinghouse overbilled a net $26,917 in escalation costs and...

Review of Non-Time Critical Kingston Ash Recovery Project Activities

2012
2011-14109
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

On Monday December 22, 2008, the ash containment area at the Kingston Fossil Plant failed. Approximately 5.4 million cubic yards of fly ash and bottom ash were released onto land and adjacent waterways. As part of the OIG's ongoing commitment to provide oversight of the Kingston ash spill cleanup...

Watts Bar Nuclear Plant Unit 2 Project Set-Up and Management Issues Affected Cost and Schedule

2012
2010-13088
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The WBN Unit 2 construction project has experienced significant schedule and cost overruns. The project was originally expected to be completed in October 2012 at a cost of just under $2.5 billion. However, TVA will not meet these targets. On April 5, 2012, TVA announced an additional $1.5 billion...

Distributor Audit of Knoxville Utilities Board

2012
2010-13658
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited the electric system of Knoxville Utilities Board (KUB), a distributor based in Knoxville, Tennessee. The objective of the audit was to determine compliance with provisions of the power contract between TVA and KUB for the audit period July 2008 through June 2010. For fiscal year (FY)...

Pressures On, Inc.

2012
2010-13104-01
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited $15.4 million in costs billed to TVA by Pressure's On, Inc. (POI), for providing hydro blasting services at the Tennessee Valley Authority (TVA) locations, including $14.82 million in costs paid by TVA to POI as of January 16, 2009. In addition, the OIG reviewed $596,789 in costs for...

Distributor Audit of Memphis Light, Gas, and Water Division

2012
2010-13657
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The OIG audited the electric system of Memphis Light, Gas, and Water Division (Memphis), a distributor based in Memphis, Tennessee. The objective of the audit was to determine compliance with provisions of the power contract between TVA and Memphis during the period January 2009 through December...