Proposal for Civil Projects and Coal Combustion Residual Program Management Work

2018
2017-15499
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for civil projects and coal combustion residual program management work at TVA's steam electric power plants. Our examination objective was to determine if the company's cost...

Bechtel Power Corporation - Contract No. 65419

2018
2015-15319
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

As part of our annual audit plan, we performed an audit of costs billed to the Tennessee Valley Authority (TVA) by Bechtel Power Corporation (Bechtel) for providing engineering, procurement, construction, and related services in support of the completion of TVA's Watts Bar Nuclear Plant Unit 2 under...

TVA's Interruptible Pricing Products

2018
2017-15478
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

The Tennessee Valley Authority's (TVA) Interruptible Power (IP) program implemented new products in October 2015 as part of the product redesign of TVA's demand response portfolio. We initiated this audit in response to concerns forwarded to our office regarding (1) the amount of credits provided...

Proposal for Civil Projects and Coal Combustion Residual Program Management Work

2018
2017-15504
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for civil projects and coal combustion residual program management work at TVA's steam electric power plants. Our examination objective was to determine if the company's cost...

Proposal for Civil Projects and Coal Combustion Residual Program Management Work

2018
2017-15493
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for civil projects and coal combustion residual program management work at TVA's steam electric power plants. Our examination objective was to determine if the company's cost...

Proposal for Civil Projects and Coal Combustion Residual Program Management Work

2018
2017-15501
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for civil projects and coal combustion residual program management work at TVA's steam electric power plants. Our examination objective was to determine if the company's cost...

Proposal for Civil Projects and Coal Combustion Residual Program Management Work

2018
2017-15491
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for civil projects and coal combustion residual program management work at TVA's steam electric power plants. Our examination objective was to determine if the company's cost...

Restoration Services, Inc. - Contract No. 6122

2018
2017-15502
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

As part of our annual audit plan, we audited costs billed to the Tennessee Valley Authority (TVA) by Restoration Services, Inc. (RSI) for project control services for TVA's Generation Construction under Contract No. 6122. Our audit included approximately $12.5 million in costs billed to TVA from...

ThyssenKrupp Elevator Americas - Contract No. 8527

2018
2017-15462
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we performed an audit of costs billed to TVA by ThyssenKrupp Elevator Americas (TKE) for providing elevator maintenance and repair services under Contract No. 8527. Our audit included approximately $2.83 million in costs billed...

Proposal for Civil Projects and Coal Combustion Residual Program Management Work

2018
2018-15546
Audit
Tennessee Valley Authority OIG
Tennessee Valley Authority

At the request of the Tennessee Valley Authority's (TVA) Supply Chain, we examined the cost proposal submitted by a company for civil projects and coal combustion residual (CCR) program management work at TVA's steam electric power plants. Our examination objective was to determine if the company's...