To view a short video related to this report, please click the link below.
Open Recommendations
| Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
|---|---|---|---|---|---|
| 1 | No | $0 | $0 | Status as of August 31, 2025 | |
| Complete the heating, ventilation, and cooling equipment upgrade subproject at Metropolitan Detention Center Brooklyn and ensure that the equipment is capable of maintaining temperatures at BOP targets. Further, ensure that upgraded hardware and Building Management System software allow facilities staff to accurately monitor building temperatures and heating, ventilation, and cooling equipment performance. | |||||
| 2 | No | $0 | $0 | Status as of August 31, 2025 | |
| Take further action to diagnose the sources of temperature regulation issues and remedy them, if the upgraded Metropolitan Detention Center Brooklyn heating, ventilation, and cooling system cannot maintain building temperatures at BOP targets. | |||||
| 4 | No | $0 | $0 | Status as of August 31, 2025 | |
| Ensure that, in the absence of Building Management System software, institutions use a consistent and sound method to measure and document temperatures and record all maintenance performed on heating, ventilation, and cooling equipment. | |||||