Report File
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2023-17463
Report Description

The Office of the Inspector General evaluated whether TVA’s quality management process for the Colbert Combustion Turbine expansion project was accomplished in a manner to achieve compliance with quality objectives and acceptance criteria. We determine quality management was accomplished by the Engineering, Procurement, and Construction contractor in a manner to achieve compliance with quality objectives and acceptance criteria. However, due to previously identified Original Equipment Manufacturer related risks, we found TVA’s oversight of the Original Equipment Manufacturer’s equipment during fabrication could have been improved.

Report Type
Inspection / Evaluation
Agency Wide
Yes
Number of Recommendations
1
Questioned Costs
$0
Funds for Better Use
$0

Open Recommendations

This report has 1 open recommendations.
Recommendation Number Significant Recommendation Recommended Questioned Costs Recommended Funds for Better Use Additional Details
1 No $0 $0

We recommend the Senior Vice President, Generation Projects and Fleet Services, implement a process to determine the appropriate level of Original Equipment Manufacturer oversight needed for future projects.

Tennessee Valley Authority OIG