Report File
Date Issued
Submitting OIG
Department of the Interior OIG
Other Participating OIGs
Department of the Interior OIG
Agencies Reviewed/Investigated
Department of the Interior
Components
National Park Service
Report Number
2020-CR-066
Report Description

We found that the NPS was unable to effectively identify and manage its deferred maintenance due to inaccurate and unreliable data.

Report Type
Inspection / Evaluation
Agency Wide
Yes
Number of Recommendations
8
Questioned Costs
$0
Funds for Better Use
$0

Open Recommendations

This report has 2 open recommendations.
Recommendation Number Significant Recommendation Recommended Questioned Costs Recommended Funds for Better Use Additional Details
2020-CR-066-05 Yes $0 $0

We recommend that the NPS develop and implement policies and procedures that provide guidance for appropriately estimating the cost of maintenance projects.

2020-CR-066-06 Yes $0 $0

We recommend that the NPS include accurate estimates for all existing and future work orders based on the guidance developed under Recommendation 5.

Department of the Interior OIG

United States