We assessed NPS’ process for estimating and adjusting project cost estimates for construction contracts awarded using GAOA funds.
Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
2022-CGD-051-03 | No | $0 | $0 | ||
We recommend that NPS develop servicewide guidance to aid National Park Service staff when determining whether National Park Service cost estimating personnel and contracted architect and engineer firms should be required to conduct site visits when developing construction estimates. | |||||
2022-CGD-051-04 | No | $0 | $0 | ||
We recommend that NPS develop a method to track and monitor independent government cost estimate accuracy for Great American Outdoors Act Legacy Restoration Fund construction projects and develop a process to evaluate trends that lead to inaccurate estimates, to include the types of construction projects. |