Skip to main content
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2007-11189
Report Description

As part of our annual audit plan, we audited $5.2 million in costs billed to TVA by a contractor for subcontract services provided on the Browns Ferry Nuclear Plant Unit 1 (BFN U1) recovery project. Under its subcontract, the subcontractor provided engineers for the BFN U1 project to assist in the resolution of technical issues developed during the field implementation of modifications. Our audit objective was to determine if the costs the contractor billed to TVA were in compliance with the provisions of the contract and the subcontract. In summary, we determined the contractor billed TVA $25,331 for costs that were not in accordance with the contract provisions. TVA management plans to recover the overbilled costs. Summary Only

Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0

Tennessee Valley Authority OIG