We determined TVA had been overbilled $103,007 (out of $10.9 million that had been billed) for services performed at BFN Unit 1 by a subcontractor. The overbilling included (1) unsupported labor hours, (2) ineligible fees that had been applied to travel and relocation costs, and (3) ineligible jury duty hours. TVA is assessing our recommendations. Summary Only
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2005-019C
Report Description
Report Type
Audit
Questioned Costs
$0
Funds for Better Use
$0