Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
24-A-04-003.01 | No | $0 | $0 | ||
We recommend that ASPR mitigate the risk presented by relying on foreign supply chains and JIT inventory strategies when determining annual Stockpile purchases. | |||||
24-A-04-003.02 | No | $0 | $0 | ||
We recommend that ASPR develop a strategic plan for the Stockpile, that clearly defines the goals and objectives of the Stockpile, and the Stockpile's roles and responsibilities for responding to emergency events, including pandemics. | |||||
24-A-04-003.03 | No | $0 | $0 | ||
We recommend that ASPR work to increase the Stockpile's annual funding to keep pace with the Stockpile's increased responsibilities. | |||||
24-A-04-003.04 | No | $0 | $0 | ||
We recommend that ASPR reinstate the annual planning and review process and issue to Congress an updated PHEMCE SIP, PHEMCE Multiyear Budget, and Stockpile Annual Review Report. | |||||
24-A-04-003.05 | No | $0 | $0 | ||
We recommend that ASPR develop a plan and timeline for fully integrating the Stockpile within ASPR. | |||||
24-A-04-003.06 | No | $0 | $0 | ||
We recommend that ASPR develop a response plan, to include communication plans, for situations in which the Stockpile needs to respond to changes in roles and responsibilities during large-scale emergency responses. |