Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2005-044C
Report Description

We reviewed a contractor's material cost adjustments and profit sharing calculations and determined the contractor (1) had understated the material cost adjustment due TVA by $5,933 and (2) could not provide verifiable documentation of the material weights used in its catalyst production. TVA management agreed with our findings and is taking action to recover the amount owed to TVA. Additionally, since the contractor could not provide verifiable documentation of its material weights, TVA is negotiating a contract change to limit future cost adjustments to the contractor's preferred customer price. Summary Only

Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0

Tennessee Valley Authority OIG