USAID/Afghanistan implement a strategy, which includes milestone dates, to repair or replace the Tarakhil Power Plant's maintenance management system, provide plant staff with further training and supervision in the use of this system to enable them to manage Tarakhil's inventory control functions on their own, and facilitate a comprehensive inventory of the plant's spare parts, supplies, and nonexpendable assets.
Questioned Costs
$0
Funds for Better Use
$0
Recommendation Status
Closed
Source UUID
F-306-14-002-S-4
Recommendation Number
4
Significant Recommendation
No