We audited $3.8million of costs billed to TVA by a contractor for providing reclearing and maintenance for transmission line right-of-way areas. In summary, we found the contractor could not provide support for an estimated $33,521 in labor costs. The contractor agreed with our finding and explained that on several occasions employees had been paid in cash. TVA management plans to recover the unsupported costs.
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2007-11047
Report Description
Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0