Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2007-015C
Report Description

We audited $23.2 million of costs billed by a TVA contractor for providing construction and modification services for TVA's generating plant switchyards, substations, electrical transmission system, and power control communication facilities. We found the costs billed by the contractor were fairly stated except for a minor overbilling of craft labor costs that occurred as a result of a clerical error. Summary Only

Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0