We performed a pre-implementation review of the Enterprise Asset Management (EAM) System, Phase 1 implementation, which provided for supply chain and work management processes. We determined plans and processes in place were adequate after actions were completed to address our concerns, regarding application access controls, system security, system testing, data conversion, and general controls. During our audit, the EAM Project Team and Information Services took actions to address our findings and initiated plans to implement additional corrective actions and address remaining concerns during subsequent system implementation phases. Summary Only
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2008-11792
Report Description
Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0