To examine the readiness of NASA’s acquisition workforce to respond to current and future contracting needs.
Report File
Date Issued
Submitting OIG
National Aeronautics and Space Administration OIG
Other Participating OIGs
National Aeronautics and Space Administration OIG
Agencies Reviewed/Investigated
National Aeronautics and Space Administration
Report Number
IG-21-002
Report Description
Report Type
Audit
Agency Wide
Yes
Number of Recommendations
4
Questioned Costs
$0
Funds for Better Use
$0
Open Recommendations
This report has 1 open recommendations.
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
2 | No | $0 | $0 | ||
To help ensure the success of the MAP transformation, we recommend NASA’s Assistant Administrator for Procurement document contract assignments to COs, CORs, and program/project managers in a centralized system for inclusion in the Performance Metrics Dashboard. |