Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
2012-AT-1009-001-A | No | $3,213,572 | $0 | ||
Require the Municipality to develop and implement a financial management system in accordance with HUD requirements and ensure that $3,213,572 in HOME funds drawn from HUD between July 1, 2009, and December 31, 2011, can be traced to a level which ensures that such funds have not been used in violation of the restrictions and prohibitions of applicable statutes or reimburse the HOME program from non-Federal funds.(Footnote 2) Total disbursements of $3,523,723 were adjusted to consider $173,978 questioned in recommendation 1B, $86,567 questioned in recommendation 1D, and $49,606 | |||||
2012-AT-1009-001-C | No | $114,139 | $0 | ||
Require the Municipality to submit supporting documentation showing the allocability and eligibility of $114,139 charged to the HOME program for project delivery costs or reimburse the program from non-Federal funds. | |||||
2012-AT-1009-002-B | No | $537,773 | $0 | ||
Determine the eligibility of the $537,773 disbursed for the Ciudad de Ensueo project and reevaluate the feasibility of the activity. (Footnote 9) Total disbursements of $538,973 were adjusted to consider $1,200 questioned in recommendation 1F. The Municipality must reimburse its HOME program from non-Federal funds if HUD determines the activity to have been terminated. |