CSO tank construction delays may increase taxpayer costs to complete the cleanup remedy at the Gowanus Canal Superfund site and prolong community exposure to contaminants.
Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
1 | No | $0 | $0 | ||
Closely monitor combined sewer overflow tank construction progress at the Gowanus Canal Superfund site and take immediate action, including enforcement actions if appropriate, if New York City misses any future tank project milestones from the 2021 administrative order. | |||||
2 | No | $0 | $0 | ||
Post on the EPA's public website the milestones from the 2021 administrative order regarding the Gowanus Canal Superfund site, New York City's progress towards completing these milestones, and any actions taken to ensure the city stays on schedule. |