Date Issued
Submitting OIG
Amtrak (National Railroad Passenger Corporation) OIG
Agencies Reviewed/Investigated
Amtrak (National Railroad Passenger Corporation)
Report Number
OIG-A-2026-001
Report Description

Our objective for this report was to assess the company’s efforts to support the project and oversee its interests as the project advances.

We found that Amtrak has made notable progress meeting its near-term obligations for the Hudson Tunnel Project, but the company could reduce its risks and help improve overall project performance by clarifying its role with external partners, engaging all relevant internal stakeholders, and strengthening its document management system.

To help improve overall project performance while safeguarding its interests, we recommend that the Amtrak 1) assess where interpretations of its role on the project may differ from its project partners and take steps to remedy those differences, 2) work with GDC to ensure the company has adequate, ongoing visibility into project risks on the construction packages it is not leading ,3) identify all necessary internal support activities and assign accountability for each, and 4) finalize its internal project document management system and procedures. 

Report Type
Audit
Agency Wide
Yes
Number of Recommendations
4
Questioned Costs
$0
Funds for Better Use
$0
Report updated under NDAA 5274
No

Open Recommendations

This report has 4 open recommendations.
Recommendation Number Significant Recommendation Recommended Questioned Costs Recommended Funds for Better Use Additional Details
1 Yes $0 $0

Assess where the company and its partners’ expectations of the company’s role differ. Based on this assessment, take steps to clarify the company’s role, as appropriate.

2 Yes $0 $0

Work with GDC to ensure that the company has adequate, ongoing visibility into project risks on the construction packages it is not leading.

3 Yes $0 $0

Identify and document all relevant internal stakeholders and their related HTP support activities, and assign accountable departments and individuals for each activity identified.

4 Yes $0 $0

Finalize the HTP internal document management system and related guidance consistent with Capital Delivery procedures.