We reviewed and evaluated the control design and documentation for the time reporting process to determine whether key financial reporting risks were addressed in the control framework. In summary, we determined process control documentation was inadequate in the areas of establishing responsibility for accurate time reporting, and monitoring of time reported, which resulted in inconsistencies in time reporting processes used at TVA sites. TVA management agreed with our findings and initiated corrective actions to improve guidance. Summary Only
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2005-034F
Report Description
Report Type
Audit
Agency Wide
Yes
Questioned Costs
$0
Funds for Better Use
$0