What We Looked AtBetween 2009 and 2011, Congress cumulatively appropriated $10.2 billion for the High Speed Intercity Passenger Rail (HSIPR) program. As of April 2019, the Federal Railroad Administration (FRA), responsible for this program, has disbursed $8.5 billion of those funds, with approximately 35.5 percent dedicated to developing a corridor in California, managed by the California High Speed Rail Authority (CHSRA). The former Chairman of the House Committee on Transportation and Infrastructure, Subcommittee on Railroads, Pipelines, and Hazardous Materials requested that we review FRA’s risk mitigation and oversight of expenditures. Accordingly, our audit objectives were to assess FRA’s (1) risk analysis, assessment, and mitigation efforts—particularly regarding the availability of non-Federal matching funds, business plans, and financial reporting—and (2) procedures for determining whether Federal funds expended complied with applicable Federal laws and regulations. Due to the significant amount of HSIPR funds dedicated to California, our audit focused on FRA’s cooperative agreements with CHSRA. What We FoundWhile FRA took numerous actions to oversee the CHSRA agreement, FRA missed opportunities to better assess and mitigate Federal risks. Specifically, while FRA routinely found that CHSRA submissions of required planning documents were insufficient and provided CHSRA with technical assistance to improve future submissions, prior to May 2019, FRA did not document decisions on additional actions to address the repeated shortcomings. Additionally, FRA’s review of documents submitted by CHSRA did not verify underlying methodologies used to create them or make an independent assessment of their plausibility. FRA did not define minimum standards for the acceptable interim use of the project’s Central Valley segment to ensure that the initial construction segment would have independent operational utility, or ensure that CHSRA developed an acceptable interim use plan—although CHSRA missed the deadline to provide one. Finally, FRA’s review of project reimbursement requests relied on documentation that was not adequate to verify that expenditures met Federal requirements, and FRA’s review of expenditure documentation was inadequate in some cases. Our RecommendationsWe made four recommendations to improve FRA’s assessment and mitigation of risks, documentation of decisions, and processes for overseeing expenditures. FRA concurred with three recommendations and partially concurred with one. We consider all four recommendations resolved but open pending completion of planned actions.
Date Issued
Submitting OIG
Department of Transportation OIG
Other Participating OIGs
Department of Transportation OIG
Agencies Reviewed/Investigated
Department of Transportation
Components
Federal Railroad Administration
Report Number
ST2020015
Report Description
Report Type
Audit
Agency Wide
Yes
Number of Recommendations
4
Questioned Costs
$0
Funds for Better Use
$0