Ginnie Mae generally followed Federal guidance in precrisis planning and executed its crisis management strategy with respect to the COVID-19 pandemic. However, it does not have an agencywide crisis readiness plan, addressing likely hazards arising from a crisis, or include all key elements in line with crisis guidance from CIGFO.
Report File
Date Issued
Submitting OIG
Department of Housing and Urban Development OIG
Other Participating OIGs
Department of Housing and Urban Development OIG
Agencies Reviewed/Investigated
Department of Housing and Urban Development
Components
Ginnie Mae
Report Number
2023-KC-0004
Report Description
Report Type
Audit
Agency Wide
Yes
Number of Recommendations
0
Questioned Costs
$0
Funds for Better Use
$0
Open Recommendations
This report has 1 open recommendations.
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
2023-KC-0004-002-A | No | $0 | $0 | ||
Develop and implement an agencywide crisis readiness plan addressing likely hazards arising from a crisis. This guidance should include all key elements that meet CIGFO crisis guidance. |