We determined a contractor overbilled TVA $563,773 (out of $6.2 million that had been billed) for providing welding services for various nuclear projects. The overbilling included (1) labor costs due to the contractor's use of incorrect labor rates, misclassifications of personnel, and unsupported labor hours; (2) ineligible or unsupported mobilization, travel, and per diem costs; (3) direct billed overhead labor; and (4) duplicate costs. TVA agreed with most of our findings and is working with the contractor to resolve the overbillings. Summary Only
Date Issued
Submitting OIG
Tennessee Valley Authority OIG
Other Participating OIGs
Tennessee Valley Authority OIG
Agencies Reviewed/Investigated
Tennessee Valley Authority
Report Number
2005-004C-01-02
Report Description
Report Type
Audit
Questioned Costs
$0
Funds for Better Use
$0