Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
4 | No | $0 | $0 | ||
We recommend the Architect of the Capitol (AOC) consider tying the start of contractual warranty periods to Final Completion, rather than Substantial Completion, to ensure that the AOC does not lose warranty coverage on work completed after Substantial Completion, and to incentivize the timely completion of all work needed to meet Final Completion, including punchlist items. | |||||
7 | No | $0 | $0 | ||
We recommend for those items categorized as punchlist (in-scope work) and completed during and/or after the warranty period, the Cannon House Office Building Renewal Project team should negotiate an extended warranty period with the Construction Manager as Constructor to the extent legally and administratively feasible. | |||||
9 | No | $0 | $0 | ||
We recommend the Cannon House Office Building Renewal (CHOBr) Project team review all punchlist items discovered during the one-year warranty inspection to determine how the quality control (QC) reviewers overlooked those items during prior inspections and whether the CHOBr Project team should make any improvements to the QC process to avoid future oversights. |