Open Recommendations
| Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
|---|---|---|---|---|---|
| 1 | No | $0 | $0 | ||
| Update the Facility Security Risk Management Program Internal Operating Procedure (IOP) to include. | |||||
| 2 | No | $0 | $0 | ||
| Develop and implement policies and procedures for centrally obtaining, tracking, and analyzing security incident reports agency-wide. | |||||
| 3 | No | $0 | $0 | ||
| Develop and implement standard operating procedures (SOPs) that instruct CORs on the invoice approval process, to include a requirement that CORs document their reconciliation of invoices with detailed timesheets before security guard contract invoices are paid. | |||||
| 4 | Yes | $158,880 | $0 | ||
| Recover or otherwise resolve the $158,880.29 in questioned costs from security guard vendors as a result of insufficient documentation. | |||||
| 5 | No | $0 | $0 | ||
| Provide training on the new documentation requirements to any COR responsible for security guard contracts. | |||||
| 6 | Yes | $9,094 | $0 | ||
| Recover or otherwise resolve the $9,093.65 in questioned costs from the security guard vendor at the Truman Presidential Library related to unallowable supply and material charges. | |||||
| 7 | No | $0 | $0 | ||
| Provide specific guidance to CORs responsible for security guard contracts or, as appropriate, issue a contract modification which further clarifies the allowable uses for the “Additional Services” Contract Line Item Numbers (CLINs), and processes required to use available funds for other purposes. | |||||