| Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
|---|---|---|---|---|---|
| 1 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs (CA), in coordination with the Bureau of Budget and Planning, develop and implement a risk-based methodology to select programs for evaluation. CA should include the amount of funds invested and the risk to its portfolio as factors considered in the methodology. | |||||
| 4 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs, in coordination with the Bureau of Budget and Planning, map control gates for the program management methodology used for the Consular Systems Modernization program to the Department of States Managing State Projects guidance, as required by 5 Foreign Affairs Handbook-5 H-211. | |||||
| 5 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs, in coordination with the Bureau of Budget and Planning, develop and implement a plan to create documentation required by Department of State program and project management guidance (including 18 Foreign Affairs Manual 300) for the overall Consular Systems Modernization program and discrete projects related to the program. This documentation would include, but not be limited to, a program monitoring plan, a logic model, and a situational analysis. | |||||
| 7 | No | $0 | $0 | ||
| OIG recommends that if, following implementation of Recommendation 6, the Bureau of Consular Affairs (CA) determines that its current program management methodology is not optimal, CA should develop and implement a plan of action, in coordination with the Bureau of Budget and Planning, to adopt a different program and project management methodology that aligns with Department of State program and project management guidance. | |||||
| 8 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs, in coordination with the Bureau of Budget and Planning, perform an internal control gap analysis related to program and project management of the Consular Systems Modernization program to identify key controls that are needed to comply with Government Accountability Office requirements for maintaining a sufficient internal control environment. | |||||
| 9 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs, in coordination with the Bureau of Information Resource Management, develop and implement a mechanism to track required IT governance reviews to ensure that all governance reviews of IT systems have been completed. | |||||
| 10 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs, in coordination with the Bureau of Budget and Planning, develop and implement a process to periodically assess program and project management activities related to the Consular Systems Modernization program. | |||||
| 11 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Consular Affairs, in coordination with the Bureau of Budget and Planning and the Bureau of Information Resource Management, develop and implement a process to annually verify that designated project managers assigned to the Consular Systems Modernization program meet qualification requirements specified in 5 Foreign Affairs Manual 623.2 and the Federal IT Project Manager Guidance Matrix. | |||||
| 12 | No | $0 | $0 | ||
| OIG recommends that if project managers as described in Recommendation 11 are identified as not meeting qualification requirements, the Bureau of Consular Affairs, in coordination with the Bureau of Budget and Planning and the Bureau of Information Resource Management, develop and implement a plan of action to provide training and guidance to the project managers so that they comply with 5 Foreign Affairs Manual 623.2 and the Federal IT Project Manager Guidance Matrix. | |||||
| 16 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Administration, in coordination with the Bureau of Consular Affairs, develop and implement bureau-specific procedures requiring CAs assigned Contracting Officers Representatives to (a) maintain documentation of their invoice review that demonstrates that costs and supporting documentation were verified and (b) confirm that labor hours billed had supporting documentation that was sufficient to support the approval for payments. | |||||
| 19 | No | $0 | $0 | ||
| OIG recommends that the Bureau of Administration, in coordination with the Bureau of Consular Affairs, develop and implement procedures to ensure that Contracting Officers Representatives who oversee Consular Systems Modernization program task orders complete and submit reports in the Contractor Performance Assessment Reporting System within the required 120 days. | |||||