Open Recommendations
| Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
|---|---|---|---|---|---|
| 4 | No | $177,662 | $0 | ||
| We recommend that the contracting officer require the Plan to return $177,662 to the FEHBP for the questioned uncollected claim overpayments, whether recovered or not, as diligent efforts to recover these overpayments were not made. If the Plan repays these questioned overpayments of $177,662 to the FEHBP during the audit resolution process, then the contracting officer should allow the Plan to keep whatever funds are subsequently recovered for these overpayments. | |||||