Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
D-2024-0055-D000AT-0001-0001.A1b | No | $872,309 | $0 | ||
Rec. A.1.b: The DoD OIG recommended that the Commanding General, Army Mission and Installation Contracting Command require the contracting officials to recalculate the prior award-fee amounts earned by the contractor to identify overpayments. The calculation should be done for the current and previous contract this contractor was awarded. Once that is complete, the Commanding General should require the contracting officer to pursue compensation from the contractor for overpayments, including the $872,309 identified in this report. | |||||
D-2024-0055-D000AT-0001-0002.A2a | No | $0 | $0 | ||
Rec. A.2.a: The DoD OIG recommended that the Deputy Assistant Secretary for Contracting, Office of the Assistant Secretary of the Air Force (Acquisition, Technology, and Logistics), direct the Air Force Nuclear Weapons Center Director of Contracting to establish and implement a process that ensures contracting officials do not allow the contractor to begin work without an approved award-fee plan that documents how the contractor's performance will be assessed. | |||||
D-2024-0055-D000AT-0001-0002.A2b | No | $0 | $0 | ||
Rec. A.2.b: The DoD OIG recommended that the Deputy Assistant Secretary for Contracting, Office of the Assistant Secretary of the Air Force (Acquisition, Technology, and Logistics), direct the Air Force Space Systems Center Director of Contracting to establish and implement a process that ensures contracting officials support and justify any award-fee changes within the contract file in a timely manner. | |||||
D-2024-0055-D000AT-0002-0001.B1a | No | $0 | $0 | ||
Rec. B.1.a: The DoD OIG recommended that the Assistant Secretary of the Army (Acquisition, Logistics, and Technology) implement controls sufficient to ensure that contracting officials are following Federal and DoD requirements related to administration and management of cost-plus-award-fee contracts. | |||||
D-2024-0055-D000AT-0002-0001.B1b | No | $0 | $0 | ||
Rec. B.1.b: The DoD OIG recommended that the Assistant Secretary of the Navy (Research, Development, and Acquisition) implement controls sufficient to ensure that contracting officials are following Federal and DoD requirements related to administration and management of cost-plus-award-fee contracts. | |||||
D-2024-0055-D000AT-0002-0001.B1c | No | $0 | $0 | ||
Rec. B.1.c: The DoD OIG recommended that the Deputy Assistant Secretary for Contracting, Office of the Assistant Secretary of the Air Force (Acquisition, Technology, and Logistics) implement controls sufficient to ensure that contracting officials are following Federal and DoD requirements related to administration and management of cost-plus-award-fee contracts. | |||||
D-2024-0055-D000AT-0003-0001.C1a | No | $0 | $0 | ||
Rec. C.1.a: The DoD OIG recommended that the Defense Pricing and Contracting Principal Director, in coordination with the Military Departments and Defense agencies, establish and implement a solution to accurately capture all relevant cost-plus-award-fee data. | |||||
D-2024-0055-D000AT-0003-0001.C1b | No | $0 | $0 | ||
Rec. C.1.b: The DoD OIG recommended that the Defense Pricing and Contracting Principal Director, in coordination with the Military Departments and Defense agencies, evaluate the effectiveness of the award fees paid. |