Report File
Date Issued
Submitting OIG
Department of War OIG
Other Participating OIGs
Department of War OIG
Agencies Reviewed/Investigated
Department of War
Report Number
DODIG-2025-017
Report Type
Audit
Agency Wide
Yes
Number of Recommendations
2
Questioned Costs
$0
Funds for Better Use
$0
Report updated under NDAA 5274
No

Open Recommendations

This report has 4 open recommendations.
Recommendation Number Significant Recommendation Recommended Questioned Costs Recommended Funds for Better Use Additional Details
D-2025-0017-D000AV-0001-0001.e No $0 $0

(U) Rec. 1.e: The DoD OIG recommended that the Commander, Naval Facilities Engineering Systems Command, review the Land Use Control plan development process and update that process to address coordination with multiple stakeholders, and methods to streamline revisions.

D-2025-0017-D000AV-0001-0001.f No $0 $0

(U) Rec. 1.f: The DoD OIG recommended that the Commander, Naval Facilities Engineering Systems Command, develop and issue Naval Facilities Engineering Systems Command supplemental guidance to the Unified Facilities Guide Specifications, Section 01 91 00.15, Building Commissioning, that includes developing specific project schedules and establishing a regular schedule to discuss commissioning with all stakeholders early in the military construction process.

D-2025-0017-D000AV-0001-0001.g No $0 $0

(U) Rec. 1.g: The DoD OIG recommended that the Commander, Naval Facilities Engineering Systems Command, coordinate with Marine Corps Headquarters and Manpower Management Officer Assignment Command officials to issue guidance establishing mutual expectations for staffing the Site Activation Task Force to military construction projects to ensure timely and sufficient staffing of future military construction projects.

D-2025-0017-D000AV-0001-0002 No $0 $0

(U) Rec. 2: The DoD OIG recommended that the Deputy Assistant Secretary of Defense for Infrastructure Modernization and Resilience, in coordination with the Deputy Assistant Secretary of Defense for Environmental Management and Restoration, issue guidance emphasizing to personnel the importance of: 1) identifying situations where Per- and Polyfluoroalkyl Substance-impacted soil and water may be encountered during military construction projects; and 2) including all reasonable costs to manage Per- and Polyfluoroalkyl Substance-impacted soil and water when completing DD Form 1391, FY _____ Military Construction Project Data, for all future military construction projects.