Rec. 1.a: The DoD OIG recommended that the U.S. Army Corps of Engineers Chief of Engineering and Construction issue a memorandum and provide training to U.S. Army Corps of Engineers personnel emphasizing guidance to: 1. Develop accurate construction-related estimates on future military construction contract solicitations. 2. Estimate cost and schedule for possible variations in the soil conditions based on a geotechnical report and weather conditions of the location of future military construction projects. 3. Use the quality management system, including how to categorize and access lessons learned from previous military construction projects, and the importance of reviewing after-action reviews to identify lessons learned from previous military construction projects in preparation for future military construction projects.