Sorry, you need to enable JavaScript to visit this website.
Skip to main content
Report File
Date Issued
Submitting OIG
Architect of the Capitol OIG
Agencies Reviewed/Investigated
Architect of the Capitol
Report Number
OIG-AUD-2025-02
Report Type
Audit
Agency Wide
Yes
Number of Recommendations
2
Questioned Costs
$0
Funds for Better Use
$0
Report updated under NDAA 5274
No

Open Recommendations

This report has 1 open recommendations.
Recommendation Number Significant Recommendation Recommended Questioned Costs Recommended Funds for Better Use Additional Details
2 No $0 $0

We recommend that the Architect of the Capitol develop construction contract requirements and project specifications for substantial and final completion that are feasible, achievable and necessary for future construction projects with multiple phases — similar to the Cannon House Office Building Renewal Project.

Architect of the Capitol OIG

United States