Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
1 | No | $0 | $0 | ||
We recommend that the Architect of the Capitol revise and fully implement a process that ensures compliance with construction contracts, project specifications and any other requirements prescribed for substantial and final completion and document justification and approval for all deviations. This process should be applied to the awarding of substantial and final completion on all remaining Phases of the Cannon House Office Building Renewal Project. | |||||
2 | No | $0 | $0 | ||
We recommend that the Architect of the Capitol develop construction contract requirements and project specifications for substantial and final completion that are feasible, achievable and necessary for future construction projects with multiple phases — similar to the Cannon House Office Building Renewal Project. |