Skip to main content
Report File
Date Issued
Submitting OIG
Department of Defense OIG
Agencies Reviewed/Investigated
Department of Defense
Report Number
DODIG-2025-059
Report Type
Audit
Agency Wide
Yes
Number of Recommendations
14
Questioned Costs
$0
Funds for Better Use
$0
Report updated under NDAA 5274
No

Open Recommendations

This report has 14 open recommendations.
Recommendation Number Significant Recommendation Recommended Questioned Costs Recommended Funds for Better Use Additional Details
D-2025-0059-D000AX-0001-0001 No $0 $0

(U) Rec 1: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures to establish realistic qualifying proposal due dates in definitization schedules, including considering size and complexity of requirements, historical time frames of the contractor providing proposals, and other programs requiring proposals from the same contractor.

D-2025-0059-D000AX-0001-0002 No $0 $0

(U) Rec 2: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures to update definitization schedule time frames when the Government makes changes to the original requirements, depending on the extent of changes.

D-2025-0059-D000AX-0001-0003 No $0 $0

(U) Rec 3: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures and provide training to contracting personnel on when to withhold payments from contractors that do not provide qualifying proposals in accordance with the definitization schedule.

D-2025-0059-D000AX-0001-0004 No $0 $0

(U) Rec 4: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures to ensure that contracting officers document, in the contract file, the justification for withholding payments or not withholding payments from contractors that do not provide qualifying proposals in accordance with the definitization schedule.

D-2025-0059-D000AX-0001-0005 No $0 $0

(U) Rec 5: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement policy to standardize how contracting personnel establish and document in the contract file the beginning of the 180?day period to definitize.

D-2025-0059-D000AX-0001-0006 No $0 $0

(U) Rec 6: The DoD OIG recommended that the Commanding General, Army Contracting Command provide training to contracting personnel to clarify that the 180?day period to definitize the undefinitized contract action begins on the date the contractor submits the qualifying proposal, in accordance with the United States Code.

D-2025-0059-D000AX-0001-0007 No $0 $0

(U) Rec 7: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures to ensure that contracting personnel engage with the Defense Contract Audit Agency and Defense Contract Management Agency before obtaining contractor proposals when they determine that a Defense Contract Audit Agency or Defense Contract Management Agency audit will be required for the undefinitized contract action.

D-2025-0059-D000AX-0001-0008 No $0 $0

(U) Rec 8: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures to ensure that contracting personnel require contractors to submit Defense Federal Acquisition Regulation Supplement proposal adequacy checklists with proposals, in accordance with the Defense Federal Acquisition Regulation Supplement, and ensure contracting personnel review Defense Federal Acquisition Regulation Supplement proposal adequacy checklists to verify that proposals are adequate before submitting the proposals to the Defense Contract Audit Agency or Defense Contract Management Agency for their proposal audits.

D-2025-0059-D000AX-0001-0009 No $0 $0

(U) Rec 9: The DoD OIG recommended that the Commanding General, Army Contracting Command issue a memorandum requiring contracting personnel to request a waiver of the definitization schedule, when appropriate, and detailing the circumstances in which a waiver should be requested.

D-2025-0059-D000AX-0001-0010 No $0 $0

(U) Rec 10: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement policy to establish meetings between contracting officials at each contracting activity and contractors on a regular and recurring basis to improve communication and determine responsibilities and impediments, along with a course of action for definitizing undefinitized contract actions within the 180?day requirement.

D-2025-0059-D000AX-0001-0011 No $0 $0

(U) Rec 11: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures and provide training to contracting personnel on how and when to unilaterally definitize undefinitized contract actions.

D-2025-0059-D000AX-0001-0012 No $0 $0

(U) Rec 12: The DoD OIG recommended that the Commanding General, Army Contracting Command issue a memorandum requiring contracting personnel to use the most current version of DD Form 1547, "Record of Weighted Guidelines Application," when completing weighted guidelines analysis on all negotiated undefinitized contract actions when certified cost or pricing date is obtained.

D-2025-0059-D000AX-0001-0013 No $0 $0

(U) Rec 13: The DoD OIG recommended that the Commanding General, Army Contracting Command develop and implement procedures to ensure that contracting officers assess the extent of incurred costs when definitizing undefinitized contract actions and prepare the DD Form 1547, "Record of Weighted Guidelines Application," including separating incurred costs from estimated costs to complete and applying separate risk factors based on the reduced cost risk to the contractor.

D-2025-0059-D000AX-0001-0014 No $0 $0

(U) Rec 14: The DoD OIG recommended that the Commanding General, Army Contracting Command Develop and implement procedures to ensure that contracting officers document their consideration of reduced cost risk during the undefinitized period and rationale for the assigned contract type risk values in price negotiation memorandums.

Department of Defense OIG

United States