The Office of the Inspector General conducted an evaluation of Lagoon Creek Combustion Turbine Plant (LCCT) to identify strengths and risks that could impact LCCT’s organizational effectiveness. Our evaluation identified strengths related to (1) teamwork and (2) organizational alignment. However, we also identified issues that could pose risks to LCCT’s effectiveness and its continued ability to meet its responsibilities. These issues related to (1) low morale caused by a lack of accountability and (2) perceptions of unethical behavior.
Date Issued:
Thursday, April 12, 2018
Agency Reviewed / Investigated:
Submitting OIG-Specific Report Number:
2018-15524
Location(s):
Agency-Wide
Type of Report:
Inspection / Evaluation
Questioned Costs:
$0
Funds for Better Use:
$0
Number of Recommendations:
2