Submitting OIG:
Report Description:
The objectives of the audit were to determine whether (1) costs incurred under the award were allowable, allocable, and reasonable; (2) the method chosen for obtaining construction services was effective and efficient; and (3) the power system is working and delivered as intended.
Short / Alternative Report Title:
Power System Upgrade Grant
Date Issued:
Thursday, January 7, 2016
Agency Reviewed / Investigated:
Submitting OIG-Specific Report Number:
DCOIG-16-003-A
Component, if applicable:
Energy Program
Location(s):
Ruby, AK
United StatesType of Report:
Audit
Questioned Costs:
$1,040
Funds for Better Use:
$0
Number of Recommendations:
1
View Document:
Attachment | Size |
---|---|
DCOIG-16-003-A.pdf | 769.08 KB |