The Office of the Inspector General conducted a review of the Ackerman Combined Cycle Plant (AKC) to identify factors that could impact AKC’s organizational effectiveness. During our evaluation, plant personnel informed us the culture at the plant was generally positive due to strong engagement between team members and with plant management. However, plant personnel informed us of operational concerns regarding (1) the plants grounding process, (2) work management, and (3) a valve that was not operating properly. Management subsequently addressed the valve concern and is in the process of addressing the concerns related to the grounding process.
Date Issued:
Wednesday, October 26, 2022
Agency Reviewed / Investigated:
Submitting OIG-Specific Report Number:
2022-17336
Location(s):
Agency-Wide
Type of Report:
Inspection / Evaluation
Questioned Costs:
$0
Funds for Better Use:
$0
Number of Recommendations:
2