We found BOR did not effectively design and implement internal controls that ensure the CVP’s cost allocation and ratesetting processes are accurate.
Short / Alternative Report Title:
Stronger Controls Needed Over BOR’s Central Valley Project Cost Allocation and Ratesetting Processes
Date Issued:
Monday, August 12, 2024
Agency Reviewed / Investigated:
Submitting OIG-Specific Report Number:
2022-WR-048
Location(s):
Agency-Wide
Type of Report:
Audit
Questioned Costs:
$1,685
Funds for Better Use:
$0
Number of Recommendations:
20