Submitting OIG:
Report Description:
We found that the IA did not adequately analyze labor rate costs added to the contract and that the DWP did not appropriately monitor the contract.
Short / Alternative Report Title:
Indian Affairs Acquisitions Can Improve Administration and Oversight of Contract No. 140A1620C0007
Date Issued:
Friday, June 9, 2023
Agency Reviewed / Investigated:
Submitting OIG-Specific Report Number:
2022-CGD-010
Component, if applicable:
Bureau of Indian Affairs
Location(s):
Agency-Wide
Type of Report:
Audit
Questioned Costs:
$1,017,180
Funds for Better Use:
$1,444,084
Number of Recommendations:
8
Report updated under NDAA 5274:
No
View Document:
Attachment | Size |
---|---|
Final-Audit-ReportBIATimeandMaterialsContractPublic.pdf | 5.36 MB |