We determined that the Federal Emergency Management Agency’s (FEMA) process for recovering disallowed grant funds could be improved. First, FEMA justified allowing most of the costs we questioned for noncompliance with procurement regulations without addressing the procurement deficiencies. Second, although staff in FEMA regional offices generally followed internal guidance when recovering disallowed grant costs, they did not track debt collections by the FEMA Finance Center because FEMA guidance does not require them to do so. Finally, FEMA did not update its internal guidance to comply with revised time limits of the statute of limitations in the Robert T. Stafford Disaster Relief and Emergency Assistance Act. We made five recommendations for FEMA to address identified deficiencies and revise its guidance. FEMA concurred with all five of our recommendations.
Open Recommendations
Recommendation Number | Significant Recommendation | Recommended Questioned Costs | Recommended Funds for Better Use | Additional Details | |
---|---|---|---|---|---|
4 | No | $0 | $0 | ||
Review and update, as necessary, all applicable policies to reflect the changes to the statute of limitations created by the Disaster Recovery Reform Act of 2018 for Section 705(a) of the Robert T. Stafford Disaster Relief and Emergency Assistance Act. | |||||
5 | No | $0 | $0 | ||
Revise FEMA’s process to routinely review all internal policies and procedures when Federal laws and regulations affecting FEMA change to ensure internal policies and procedures remain compliant and required changes are timely. |