Recommendation Details
Text of Recommendation
We recommend that, for the remaining contract phases (Phases 3 and 4), the Cannon House Office Building Renewal Project team update its written quality control procedures to ensure compliance with all requirements for punchlist items prescribed in the Construction Manager as Constructor contract and specifications.
Recommendation Number
2
Recommendation Status
Open
Significant Recommendation
No
Recommendation Questioned Costs
$0
Recommendation Funds for Better Use
$0