Text of Recommendation | We recommend the Architect of the Capitol perform the following:
a. Review the questioned costs of $6,958 identified within the Cannon House Office Building Renewal Project for potential improper overhead and profit markups by the first-tier subcontractor for a second-tier subcontractor’s work.
b. Review and modify the contract language to specify the allowable markups on change orders aligns with the memorandum dated June 26, 2017. |
---|---|
Recommendation Number | 3 |
Recommendation Status | Open |
Significant Recommendation | No |
Recommendation Questioned Costs | $6,958 |
Recommendation Funds for Better Use | $0 |