Text of Recommendation | To protect the U.S. government’s investment in ANA Camp Commando, we recommend that the Commanding General, USACE, direct the Commander, USACE Transatlantic Division, to report back to SIGAR within 90 days: Determine the circumstances leading to the acceptance of the Phase II work as completed, with full payment made to the contractor, when known deficiencies existed. Based on the results, determine what disciplinary action, if any, should be taken against the contracting officer or contracting officer’s representative. |
---|---|
Recommendation Status | Closed |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Report Title | ANA Camp Commando Phase II: Power Plant
and Fuel Point Not Fully Operational Nearly Two Years after Project Completion |
Report Submitting OIG-Specific Report Number | 15-25-IP |
Report Date Issued | Tuesday, January 6, 2015 |
Report Agency Reviewed / Investigated | |
Report Questioned Costs | $0 |
Report Funds for Better Use | $0 |