Text of Recommendation | To protect the U.S. government’s investment in ANA Camp Commando, we recommend that the Commanding General, USACE, direct the Commander, USACE Transatlantic Division, to report back to SIGAR within 90 days: Determine the amount paid to the Phase II contractor for required work that was not completed on the camp’s power plant and fuel point, and, where appropriate, recoup those funds. |
---|---|
Recommendation Status | Closed |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Report Title | ANA Camp Commando Phase II: Power Plant
and Fuel Point Not Fully Operational Nearly Two Years after Project Completion |
Report Submitting OIG-Specific Report Number | 15-25-IP |
Report Date Issued | Tuesday, January 6, 2015 |
Report Agency Reviewed / Investigated | |
Report Questioned Costs | $0 |
Report Funds for Better Use | $0 |