Text of Recommendation | We recommend that the CHOBr Project team consider amending its Change Management Plan (CMP) to require that the team perform, and document performance of a cost analysis for all PCOs with a value of less than $100,000, unless the PCO is funded using contractor contingency funds (due to contract incentive). |
---|---|