Text of Recommendation | We recommend that CHOBr Project team work with the Construction Manager as Constructor to ensure that proposals submitted for Potential Change Orders are factually sound, contain the required cost detail and exclude unallowable costs. |
---|---|
Recommendation Number | 2 |
Recommendation Status | Closed |
Significant Recommendation | No |
Recommendation Questioned Costs | $0 |
Recommendation Funds for Better Use | $0 |
Submitting OIG | |
---|---|
Linked Report |